THE WORK IN PROGRESS-the refurbishment work

Replacement of floor surface and supporting structure

Failure of the floor support structure after 120 years threatened the future of the Jubilee Hall. Its repair cost approx £35,000.An essential part of the work involved the improvement of the ventilation of the floor void and the damp proofing of the cavity Modern damp proof membranes were also used to further protect the new ‘tanalised’ floor plates and joists. Thermal insulation panels were also incorporated for the first time to retain Hall heating. Marine quality plywood sheets were then laid above the joists and insulation to provide a strong and level surface for the mounting of the high quality oak flooring strips.

Treatment of hall ceiling, and repairs to roof of annex

The beautiful vaulted ceiling helps make the Jubilee Hall very special, but it is difficult to maintain. It has suffered many attacks by woodworm over the years, and these if not treated would eventually destroy it.  The work carried out has been aimed at correcting both problems. It was carried out in the heat of a very hot summer and while our team were applying chemical dressings, temperatures in the ceiling space reached over 100 Deg. F. Access was a difficult problem and a complex system of scaffolding had to be installed, made more difficult by the weak floor upon which it stood.

It was felt that it had sufficient strength to hold the scaffolding, and it was important that the renewal of the floor should be carried towards the end of the project. With care and proper maintenance the floor surface would last many years. 

Extensive work was also a carried out to the roof of the rear annex.
Many of the timber roof joists in this area were rotten due to problems with the roof tiling and flashings, caused to some extent by Ivy penetrating the roof void. These had to be repaired or replaced, and lead gulleys and flashings were installed to ensure that there would be no further backing up of rainwater during heavy downpours.
 

 

Renewal of electrical and heating system.

Although safe, the major part of the electrical wiring system was at least twenty-five years old and coming to the end of its life. The lighting system in the main hall was also old and inadequate by modern standards. Furthermore the hall had no Public Address system and  no induction loop to help the hard of hearing. The heating distribution system was likewise elderly, using cast iron piping and cast iron column radiators that were difficult to keep clean. Protruding control knobs also represented a real risk of injury to children playing in the hall. The new lighting system has been designed specifically, at no cost, by the lighting distributor to meet our particular requirements. It provides a highly efficient and flexible system to meet the many different requirements of our hall users. 

The design and installation of the PA and Induction loop system was designed and installed by a business based in the parish, and would be of enormous benefit to many users of the Jubilee Hall. The Hall was also well equipped with power sockets, including some flush mounted in the floor. Additional power points were fitted in the roof space to facilitate the extra lighting associated with drama productions. New lights were also been fitted in the Committee Room. The heating system has been fitted with new copper piping, and the radiators replaced by finned coil heat exchangers, cased within the wainscot for safety and good appearance.

The general fabric of the hall. 

History of the parish tells us that maintaining the fabric of the hall has been an ongoing problem from the start of the last century. There is, however, no record of such a comprehensive range of work being carried out previously at one time. One of the biggest problem was the renovation of the cast iron guttering and down pipes. Believed to be the original fittings they are made of cast iron, in sizes and styles now impossible to buy. Despite extensive searching we were unable to locate some suitable replacement items at architectural reclamation yards. As a result these parts were either handcrafted to match, or repairs were carried out to the originals. All were stripped of rust and old paint and then prepared and repainted to the highest standard. It was also decided to replace some small windows where the wooden frames were rotten. The frosted glass in the large main windows was also replaced with clear glass, due to the cracks that had appeared. About ten years later it was again necessary to replace this window, with a much higher standard unit.

Another major problem was the ingress of water into the extension at the rear of the hall where the men's toilet is located. This resulted in the restructuring of the roof, and a certain amount of retiling, and the fitting of new lead flashings. Some twelve years later (2019) more work was required to solve this damp problem, which involved  fitting a waterproof membrane to the party wall. At the same time a light tube was fitted to bring natural light into the lobby area used to access the toilets and for storage.

Areas of stone and brickwork were in need of re-pointing. The front face of the Hall had also accumulated a heavy layer of dirt since it was built, and the front and side walls were pressure washed, revealing the attractive chequer board, coursed stone work that had long ago ceased to be visible.

 

Improvements and modifications to the interior.

Following on from the work on the floor and the ceiling, it became apparent that more improvements were needed and could be carried out at minimum cost. Some changes were also forced upon us due to the dilapidated condition of the hall. Sadly, it was necessary to remove the tall cupboard and the hall separator. The fascia of the former went to auction, and the latter has been recycled into the panelled wainscot. The extent of the ‘making good’ after the ceiling, floor, heatingg and electrical works also necessitated the installation of the wainscot and redecoration using a practical but modern colour scheme. It was also decided to make use of cupboard space on the upper floor to create a ‘Producers’ window and studio, complete with wiring that will facilitate, at a later date the installation of a lighting and sound control panel. This would make drama productions much easier to manage. All the toilet facilities were dramatically improved, with a new floor installed in the toilet for the disabled. In order to comply with the requirements of the Disability Discrimination Act, portable ramps are now immediately available for those who need them, and  the Hall is now as fully compliant with the legislation as is possible.

Click HERE to go to the re-Opening Event          

Click HERE to return to the Renovation Index

Click HERE to return to Introduction

February 2017